The handover appointment is the most valuable hour of the entire purchase, and it is the one most buyers walk into unprepared. A handover snagging checklist New Cairo buyers can actually work through turns that hour from a polite tour into a documented inspection. Everything you fail to record becomes your problem rather than the developer’s, because signing is not a formality: it is the moment responsibility transfers from them to you.
What follows is the order to inspect in, what matters in each room, and the small number of defects serious enough to justify not signing at all. Bring a torch, a phone charger, a spirit level if you own one, and somebody willing to be unpopular for forty minutes.
Before You Walk In
Do not go alone and do not go in a hurry
Developers schedule handovers in short slots, and a buyer on their own under time pressure records almost nothing. Bring a second person whose only job is to photograph and write while you look, and ask for a slot of at least an hour. If the appointment is offered as a fifteen minute walk through, treat that as information about how the rest of the relationship will go, and ask to rebook.
Read your contract’s finishing specification first
You cannot snag against a standard you have not read. The contract or the annexed specification says what you were sold: which finish, which brand of sanitary ware, how many power points, whether the kitchen is included. Snagging is the act of comparing what is in front of you with that document, line by line, and without it you are reduced to arguing about taste rather than about terms.
Bring the right few tools
A torch finds what ceiling lighting hides, particularly inside cupboards and under sanitary ware. A phone charger tests every socket in under a minute each. A spirit level checks a floor and a worktop faster than an eye can. A tape measure confirms that the room is the size the contract says it is, which is not always true and is extremely awkward to raise six months later.
Start With the Services, Not the Finishes
Electrics, socket by socket
Plug the charger into every socket in the apartment and watch it light. Count the points against the specification, because a missing socket is a chargeable extra later and a free correction now. Test every switch, confirm each one controls what it should, and open the distribution board to check it is labelled and that the breakers match the circuits described.
Water, pressure and drainage together
Run every tap and the shower at once, then flush the toilets while they are running. Weak pressure on a high floor, or a sudden collapse when a second outlet opens, is a building services issue rather than a tap issue and it must be raised before you sign. Fill each basin and bath, then let them drain and listen: slow drainage is a fall problem inside the wall, not something a plumber fixes in an afternoon.
Air conditioning and drainage lines
Switch every unit on and leave them running for the duration of the inspection. Look for the condensate drain and follow where it goes; a line that discharges onto a balcony floor or into a shared duct will eventually stain, smell, or both. Check that each unit’s position does not blow directly onto where a bed or a sofa is obviously going to sit.
Then the Surfaces
Floors, checked low and across the light
Crouch down and look along the floor towards a window rather than straight at it. Lippage between tiles, hollow sounding areas, chipped edges and inconsistent grout lines all appear in raking light and vanish under a ceiling fitting. Tap across the floor with a knuckle: a hollow note means the tile is not fully bedded and will crack under furniture within a year.
Walls, ceilings and the places paint hides
Run a hand over the walls and look at them from an angle. You are looking for undulation, visible patching, roller marks and the hairline cracks that appear where a block wall meets a concrete frame. Check behind where doors open, inside wardrobes and above head height, which are the three places finishing teams reliably stop caring.
Doors, windows and every moving part
Open and close every door and window fully, twice. A door that catches the frame, a window that needs force, or a handle that has to be lifted to latch is a hinge or an alignment defect, and all of them get worse as the building settles. Check that each window actually locks, that the seals are continuous, and that balcony doors drain outward rather than back into the room.

The Kitchen and Bathrooms Deserve Their Own Pass
Kitchen, if it is included
Open and close every door and drawer, check the alignment of the fronts along a run, and look underneath the worktop joints for silicone doing a job that a proper joint should be doing. Confirm the extract actually vents somewhere rather than recirculating, confirm there is a water point and a waste where the appliance is meant to go, and check the worktop is level along its full length with a spirit level.
Bathrooms, where defects are most expensive to fix later
Look for falls towards the floor drain by pouring a little water and watching where it goes; water that sits is a fall that was never cut. Check the silicone lines around the bath and tray are continuous and unbroken, that the sanitary ware matches the specified brand, and that every waste connection under the basin is dry. A bathroom defect found after you sign means lifting tiles.
Waterproofing evidence, not waterproofing promises
Ask directly whether a wet area flood test was done and whether there is a record of it. This is the single most consequential hidden item in the whole apartment, because a failed bathroom membrane appears as a stain on a neighbour’s ceiling a year later and the argument about responsibility is long and expensive.
- Photograph every defect with something in frame for scale and location
- Number each item and write the room, so the list is unambiguous
- Separate the list into defects that must be fixed before you sign and defects that can be scheduled
- Email the list the same day and ask for a written completion date
- Keep the original specification attached to your own copy
Snagging is not about being difficult. It is about being specific while being specific is still free.
What Is Worth Refusing to Sign Over
Structural, waterproofing and services failures
Hold the handover for anything structural, any evidence of water ingress, any waterproofing that cannot be evidenced, and any services defect that would need walls or floors opened to correct. These share one feature: fixing them after you have moved in means destroying finishes you have paid for, and the cost of that falls on whoever signed.
A specification that does not match the contract
If the sanitary ware, the flooring, the kitchen or the socket count is not what the contract specified, that is a contractual shortfall rather than a snag. Raise it as a shortfall, in writing, before signing. Once you sign you have accepted what is in front of you, and the substitution becomes a favour you are asking for rather than an obligation they owe.
What is reasonable to accept and schedule
Paint touch ups, a sticking door, a chipped tile edge, a missing cupboard shelf, a cracked socket faceplate: none of these justify holding the handover, and treating them as though they do costs you goodwill you will want later. Accept them onto a dated schedule with a written commitment, and keep that schedule.
After You Sign
The defects liability period is a clock, so use it
Most contracts carry a defects liability or maintenance period, often a year. Problems that only appear with use, a hairline crack as the building settles, a damp patch after the first heavy wash down, a window that leaks in the first serious rain, are covered during it. Walk the apartment deliberately at six months and again a few weeks before it expires, and submit anything you find in writing.
Do not start finishing work over an unresolved defect
The most common and most expensive mistake is building joinery, laying a new floor or papering a wall over something that was already on the snag list. It converts the developer’s obligation into your renovation problem, and it is the reason a design studio will ask to see your snag list before drawing anything.
Where a designer is useful at handover
Consultation is worth a single session at this point specifically, because an experienced eye separates a cosmetic complaint from a defect with consequences, and because the layout decisions you are about to make depend on what is actually wrong with the shell. Villa Basement Spa & Pool shows what a considered scheme looks like once the shell is sound, and How Long It Takes to Get Renovation Permits Approved in New Cairo covers what the compound will and will not let you do next.
Walk the apartment once with the contract specification in your hand and nothing else. Comparing what you were sold against what is in front of you catches more than any amount of looking for scratches.
Common Questions
Can I refuse to take handover entirely?
Usually yes, if the defects are material, but the contract governs it and delay may carry its own consequences for you. Raise material defects in writing, ask for a corrected handover date, and take advice before refusing outright rather than deciding in the room.
Should I pay for a professional snagging inspection?
For a finished apartment of any real value it is almost always worth it, because a professional finds services and waterproofing problems a buyer cannot see and produces a report in a form the developer is used to answering. Treat it as insurance against the items that need walls opened.
How long should the inspection take?
Allow an hour for a modest apartment and considerably more for a large one. Anything under thirty minutes is a walk through rather than an inspection, and the defects that matter most are the ones that need a tap left running and a torch pointed into a cupboard.
What if I already signed and then found a problem?
You are not without recourse. The defects liability period still applies to anything that qualifies as a defect rather than wear, so document it, submit it in writing immediately, and keep every reply. What you have lost is leverage, not rights.
Free guide
The Renovation Process in New Cairo, Step by Step
Leave your details and we will email you the guide on this subject straight away.
One guide, no repeat mailings.
Your guide is on its way
Check your inbox in a few minutes. If it is not there, look in your spam folder.